Generator Interconnection

Order 845 2018

FERC Order 845 (2018) — Reform of Generator Interconnection Procedures and Agreements

Order 845 (RM17-8-000, April 2018) reformed large generator interconnection procedures with surplus interconnection service, improved public data posting, and updated study processes for wind, solar, and evolving resource types.

Reference page · Issued 2018 · Updated 2026-07-15

What This Order Did

Order No. 845, issued in April 2018 in Docket RM17-8-000, reformed the large generator interconnection procedures to better accommodate the evolving resource mix, particularly variable energy resources like wind and solar. By 2018, interconnection queues were increasingly dominated by renewable and hybrid projects, yet LGIP rules from Order 2003 had not fully addressed repowering, co-located storage, and surplus capacity at existing points of interconnection.

A key innovation was surplus interconnection service, which allows generators to use spare capacity at an existing interconnection point without triggering a full new interconnection study. For example, a wind farm operating below its approved capacity could add a co-located battery within unused headroom, reducing cost and timeline compared to a greenfield interconnection request. FERC established eligibility criteria, study requirements, and tariff provisions governing how surplus service is requested and granted.

The order required transmission providers to post more interconnection-related information publicly, improving transparency for developers evaluating queue positions and upgrade costs. Order 845 also updated study processes to reflect modern grid conditions, including revised modeling assumptions for variable resources and clearer rules for processing modifications to existing interconnection agreements. These reforms modernized the interconnection framework as the power system transitioned toward a cleaner resource mix.

Order 845-A addressed rehearing requests and clarified surplus service provisions. While Order 2023 later overhauled queue administration with cluster studies, Order 845's surplus interconnection and transparency reforms remain important for developers expanding or repowering at existing sites. The order built directly on Order 2003's LGIP/LGIA foundation.

Order 845 revised how transmission providers evaluate requests to increase generating facility capacity, add energy storage, or change technology at existing sites, reducing barriers to repowering aging wind turbines with modern equipment. The order strengthened affected system study coordination and required more detailed queue data posting so developers could assess restudy risk before committing capital. FERC found that incremental reforms were necessary before broader queue overhauls because renewable repowering and hybrid projects were stalling on procedural uncertainty even when physical interconnection headroom existed at the point of interconnection.

Order 845 required transmission providers to process interconnection-related data requests more consistently and to explain study methodologies used for variable resources. These transparency measures foreshadowed the deeper queue reforms in Order 2023 while delivering immediate benefits to developers expanding operating projects. Surplus service provisions remain widely used for co-located storage and repowering at existing renewable sites. The reforms reduced study burdens for incremental additions that did not require new POIs.

845
Order Number
2018
Year Issued
Generator Interconnection
Category

Who It Applies To

  • Interconnection customers seeking surplus capacity at existing interconnection points
  • Wind and solar developers repowering or adding co-located storage to operating projects
  • Transmission providers updating LGIP study methods and public data postings
  • Hybrid resource developers combining generation and storage at a single POI

Key Holdings & Requirements

  • Established surplus interconnection service for using unused capacity at existing POIs.
  • Required expanded public posting of interconnection queue and study information.
  • Updated LGIP study processes for variable energy resources and modern grid conditions.
  • Clarified rules for material modifications and agreements governing expanded facilities.
  • Preserved Order 2003's LGIP/LGIA framework while modernizing key procedural elements.

Frequently asked questions

What is surplus interconnection service?

Surplus interconnection service lets a generator use unused interconnection capacity at an existing point of interconnection—for example, adding storage within capacity already approved for a wind farm—without a full new interconnection study. Order 845 defined how developers request and qualify for this service.

Did Order 845 replace Order 2003?

No. Order 845 amended the LGIP and LGIA framework from Order 2003, adding surplus service, transparency requirements, and updated study processes. Order 2023 later reformed queue administration further with cluster studies and readiness milestones.

Why was Order 845 needed before Order 2023?

Order 845 addressed resource-specific integration issues—surplus capacity, repowering, and data transparency—as renewable deployment accelerated. Order 2023 then tackled the broader queue backlog with cluster studies and anti-speculation milestones. The orders are complementary reforms.