Generator Interconnection

Order 2003 2003

FERC Order 2003 (2003) — Standardization of Generator Interconnection Agreements and Procedures

Order 2003 (RM02-1-000, July 2003) standardized large generator interconnection through pro forma LGIP and LGIA documents, setting study timelines, cost responsibilities, and queue procedures for projects above 20 MW.

Reference page · Issued 2003 · Updated 2026-07-15

What This Order Did

Order No. 2003, issued in July 2003 in Docket RM02-1-000, standardized the interconnection procedures and agreements for large generators—generally facilities greater than 20 MW—seeking to connect to the interstate transmission grid. Before Order 2003, each transmission provider used its own interconnection agreements and study processes, creating uncertainty for developers and barriers to entry for new generation investment.

FERC established the Large Generator Interconnection Procedures (LGIP) and Large Generator Interconnection Agreement (LGIA) as pro forma documents that all transmission providers must use. The LGIP defines the study sequence—feasibility, system impact, and facilities studies—along with timelines, cost responsibility rules, and queue management procedures. The LGIA is the binding contract governing construction of interconnection facilities, network upgrades, commercial operation milestones, and operating obligations once a project synchronizes to the grid.

The order distinguished Energy Resource Interconnection Service (ERIS), which allows injection at the point of interconnection subject to curtailment, from Network Resource Interconnection Service (NRIS), which treats the generator as a network resource for delivery to load. Developers choose the service level based on how they intend to sell output. Order 2003 set clear milestones for site control, financial deposits, and commercial operation, giving banks and investors greater certainty when financing large generation projects.

The order implemented a serial, first-come, first-served queue in which each interconnection customer bore the cost of network upgrades its project triggered. While this model provided transparency, it later proved inefficient as renewable energy surged and queues ballooned—leading to Order 2023's cluster reforms. Orders 2003-A and 2003-B addressed rehearing requests and refined study and cost provisions. Order 2003 remains the foundational interconnection framework that later orders including 845 and 2023 amended.

The LGIP established study deposit requirements, dispute resolution procedures, and rules for affected systems whose facilities may require reinforcement when new generation connects nearby. Interconnection customers must demonstrate site control and pay for interconnection facilities from the point of change of ownership to the point of interconnection, while network upgrades addressing broader system needs are allocated under defined cost responsibility rules. Order 2003 harmonized definitions across regions so developers could finance projects with predictable milestones—feasibility, system impact, and facilities studies—each with Commission-approved timelines. The standardization effort responded to explosive growth in independent power development and remains the structural backbone of U.S. generator interconnection regulation.

By replacing utility-specific agreements with mandatory pro forma documents, Order 2003 gave FERC direct oversight of interconnection terms that previously varied widely across regions. The order's serial queue model would later draw criticism as renewable queues exploded, but its standardization of definitions, study rights, and contractual milestones remains essential to every subsequent interconnection reform.

2003
Order Number
2003
Year Issued
Generator Interconnection
Category

Who It Applies To

  • Interconnection customers developing large generating facilities above 20 MW
  • Transmission providers and transmission owners administering interconnection queues
  • Affected system operators whose facilities may require upgrades for new generation
  • Project financiers and EPC contractors relying on LGIP timelines and cost rules

Key Holdings & Requirements

  • Established pro forma LGIP and LGIA that all transmission providers must adopt.
  • Set the 20 MW threshold distinguishing large generator from small generator procedures.
  • Defined ERIS and NRIS interconnection service levels with distinct curtailment and delivery rights.
  • Created serial queue, study, and cost-responsibility frameworks for network upgrades.
  • Standardized milestones for site control, deposits, and commercial operation dates.

Frequently asked questions

What size generator is subject to Order 2003?

Order 2003 applies to large generating facilities with capacity above 20 MW. Projects at or below 20 MW generally follow the Small Generator Interconnection Procedures under Order 2006, which provide a streamlined process with simpler study requirements.

What is the difference between ERIS and NRIS?

ERIS (Energy Resource Interconnection Service) allows a generator to inject at the point of interconnection but may be curtailed when congestion limits delivery. NRIS (Network Resource Interconnection Service) provides network resource treatment for delivery to load, typically requiring additional studies and upgrades.

How did Order 2003 handle interconnection queue costs?

Under Order 2003's serial queue model, each interconnection customer generally pays for network upgrades required by its project, with later-queued projects benefiting from earlier upgrades through restudies and cost reallocation rules. Order 2023 later replaced much of this with cluster-based cost sharing.

Stay Ahead of FERC

Get daily digest emails on new FERC orders

TransANCHOR monitors FERC eLibrary around the clock and delivers AI-summarized digest emails on every new order the moment it drops. Browse past daily briefings.