Order 2023-A addressed rehearing requests on the generator interconnection queue reform rules, clarifying compliance obligations and refining specific provisions in response to industry feedback.
Reference page · Issued 2023
What This Order Did
Order 2023-A addressed rehearing requests on the generator interconnection queue reform rules, clarifying compliance obligations and refining specific provisions in response to industry feedback. FERC upheld the core reforms while providing additional implementation guidance on the cluster study process, milestone requirements, and transition rules for projects already in existing queues.