Generator Interconnection

Transitional Withdrawal Penalty

Definition

The penalty assessed by the Transmission Provider to an Interconnection Customer that entered the Transitional Cluster Study or Transitional Serial Interconnection Facilities Study and subsequently withdraws, is deemed withdrawn, or whose Generating Facility does not reach Commercial Operation. Calculated under Sections 5.1.1.1 and 5.1.1.2 of the LGIP, it compensates other Interconnection Customers for restudy costs triggered by the withdrawal.

📚

Topic Deck

Generator Interconnection

🔗

Source

FERC Pro Forma OATT / LGIP