Generator Interconnection

Transitional Serial Interconnection Facilities Study

Definition

An Interconnection Facilities Study evaluating an Interconnection Request on a serial basis during the transition to the Cluster Study Process, as set forth in Section 5.1.1.1 of the LGIP. Projects eligible for this study track are those that progressed sufficiently through the old serial queue process to proceed individually, rather than being rolled into a new batch cluster study under FERC Order 2023.

📚

Topic Deck

Generator Interconnection

🔗

Source

FERC Pro Forma OATT / LGIP