Generator Interconnection

Study Delay Penalties

Definition

Financial penalties assessed against the Transmission Provider under Section 3.9 of the LGIP for failure to complete interconnection studies by applicable deadlines. Penalty rates are $1,000 per Business Day for late Cluster Studies, $2,000 per Business Day for late Cluster Restudies and Affected System Studies, and $2,500 per Business Day for late Interconnection Facilities Studies; penalties are capped at 100% of the relevant study deposit(s) and are distributed to Interconnection Customers on a pro rata basis.

📚

Topic Deck

Generator Interconnection

🔗

Source

FERC Pro Forma OATT / LGIP