Generator Interconnection

Non-Binding Dispute Resolution

Definition

An alternative to binding arbitration established under Section 13.5.5 of the LGIP, whereby either Party may request that the Transmission Provider engage an independent, neutral decision-maker. The decision-maker must be appointed within 30 Calendar Days of the request and render a written decision within 60 Calendar Days of appointment; that decision is not binding, but the Parties may cite the record and decision in subsequent arbitration or Federal Power Act Section 206 complaint proceedings.

📚

Topic Deck

Generator Interconnection

🔗

Source

FERC Pro Forma OATT / LGIP