Generator Interconnection

Interconnection Queue OASIS Posting

Definition

The public information disclosure obligation under Section 3.5.1 of the LGIP requiring the Transmission Provider to maintain on OASIS a list of all Interconnection Requests, including for each: maximum MW output, location by county and state, substation or line where interconnection will be made, projected In-Service Date, Queue Position status, type of Interconnection Service requested, and type of Generating Facility. The identity of the Interconnection Customer is anonymized on OASIS until the customer executes an LGIA or requests its filing.

📚

Topic Deck

Generator Interconnection

🔗

Source

FERC Pro Forma OATT / LGIP