Definition
A study conducted by the Transmission Provider or third-party consultant for the Interconnection Customer to determine a list of facilities (including Transmission Provider's Interconnection Facilities and Network Upgrades identified in the Cluster Study), the cost of those facilities, and the time required to interconnect the Generating Facility with the Transmission System. This is the final study phase before the LGIA is executed and construction begins.
Topic Deck
Generator Interconnection
Source
FERC Pro Forma OATT / LGIP
Explore more
All games · Transmission Planner · Docket Defender · Energy Persona quiz