Generator Interconnection

Initial Synchronization Date

Definition

The date upon which the Generating Facility is initially synchronized to the Transmission Provider's Transmission System and upon which Trial Operation begins. The Initial Synchronization Date is a key commissioning milestone, occurring after physical interconnection is complete but before Commercial Operation is achieved following successful testing and acceptance activities.

📚