Definition

A meeting between the Transmission Provider and remaining Interconnection Customers in a cluster that must be convened within 10 Business Days of the issuance of the Cluster Restudy Report, pursuant to Section 7.5 and as defined in Section 1 of the LGIP. The meeting serves the same function as the Cluster Study Report Meeting — allowing Interconnection Customers to review updated cost assignments and decide whether to proceed to LGIA tender or withdraw from the queue.

📚