Definition
The report issued following completion of an Affected System Study pursuant to Section 9.7 of the LGIP. The Affected System Study Report identifies required Affected System Network Upgrades on the Transmission Provider's Transmission System and each Affected System Interconnection Customer's proportional cost responsibility for those upgrades.
📚
Topic Deck
Generator Interconnection
🔗
Source
FERC Pro Forma OATT / LGIP